Casting cost calculation is a sum of eleven lines, and one of them, material, is usually more than two thirds of the price. This guide shows each line, the formula behind it, and a full aluminium die casting example in rupees, so you can cost a casting or test a foundry quote.
How do you calculate casting cost?
Casting cost per piece is material (including melting loss), melting, casting machine time, labour, die or pattern amortisation and a rejection allowance, plus finishing, overheads, packing and profit. Add each line per good piece. Divide the total by the casting weight if you need cost per kg.
Casting cost = material + melting + casting machine + labour + consumables + die cost, then + rejection allowance + finishing + overheads + packing + profit
What costs go into a casting?
Cost line | What it covers | How to calculate it |
|---|---|---|
Material | Metal in the finished part plus melting loss | (Casting weight + melt loss on all metal melted) x metal rate per kg |
Melting and holding | Energy, flux, degassing and furnace labour, on every kg melted including runners that are re-melted | Metal melted x melting rate per kg |
Casting machine | Die casting machine, gravity die or moulding line time | Machine hour rate x cycle time |
Labour | Operator at the machine | Labour rate per hour x cycle time |
Consumables | Die spray, lubricant, cooling | Rupees per shot |
Die or pattern | Tool cost and maintenance spread over its life | (Tool cost + maintenance) / shots over tool life |
Rejection allowance | Porosity, cold shuts, short fills | Rejection % x cost incurred up to casting |
Finishing | Trimming, fettling, shot blasting, inspection, leak test | Process time x rate per hour, plus labour |
Overheads | Plant costs not charged directly | Overhead % x conversion cost |
Packing and freight | Returnable packaging, transport | Rupees per piece |
Profit | Supplier margin | Profit % x total cost |
The machine hour rate is the line people get wrong most often. If you are unsure how to build it, read how to calculate machine hour rate first, then come back to this table.
Costing castings in a spreadsheet that nobody can audit? Cost It Right holds machine hour rate, labour, overheads and profit masters in one place, so every casting uses the same rates. See how Cost It Right does this or book a demo.
How do you calculate casting material cost with melting loss and runners?
Material cost is the metal you must buy to make one good casting. Runners, overflows and the biscuit go back to the furnace, so they cost melting and melting loss, not the full metal price again. Ingot consumed equals casting weight plus melting loss on the whole shot weight.
Ingot consumed = casting weight + (shot weight x melt loss %)
In the example below, the casting weighs 1.20 kg and the shot weighs 1.75 kg. At 3% melt loss, ingot consumed is 1.20 + (1.75 x 0.03) = 1.2525 kg. At Rs 235 per kg, material is Rs 294.34.
Two shortcuts give the wrong answer. Charging the full shot weight (1.75 kg x Rs 235 = Rs 411.25) overstates material by Rs 116.91. Charging only the casting weight (1.20 kg x Rs 235 = Rs 282.00) understates it by Rs 12.34.
How much does melting add to casting cost?
Melting adds the energy, flux, degassing and furnace labour for every kg of metal melted. It is charged on the shot weight, not the casting weight, because runners are melted again. In the example it is Rs 19.25 per piece, about 4.5% of the cost before profit. Use your own plant figure per kg melted, since it changes with furnace type and energy price.
How do you calculate the cost of a casting? An aluminium die-cast housing in rupees
The part is an aluminium alloy gearbox cover made by high pressure die casting. All rates are assumed example inputs, not market prices. Replace them with your plant and supplier figures.
Input | Value |
|---|---|
Casting weight | 1.20 kg |
Runner, overflow and biscuit (returned to the furnace) | 0.55 kg |
Shot weight | 1.75 kg |
Ingot rate | Rs 235 per kg |
Melt loss | 3% of metal melted |
Melting and holding | Rs 11 per kg melted |
Die casting machine (400 tonne) | Rs 3,000 per hour, cycle time 60 s |
Operator | Rs 300 per hour |
Die spray and consumables | Rs 2.50 per shot |
Die | Rs 18,00,000 over 2,00,000 shots, plus Rs 2,00,000 maintenance over the same life |
Rejection allowance | 4% |
Trimming press | Rs 1,000 per hour, 18 s, with an operator at Rs 300 per hour |
Shot blasting | Rs 2.00 per piece |
Inspection and leak test | 24 s at Rs 600 per hour, with an operator at Rs 300 per hour |
Overheads | 12% of conversion cost |
Packing | Rs 6.00 per piece |
Profit | 10% |
Step | Working | Rs per piece |
|---|---|---|
1. Material | 1.2525 kg x 235 | 294.34 |
2. Melting and holding | 1.75 kg x 11 | 19.25 |
3. Casting machine | 60 s at 3,000 per hour | 50.00 |
4. Operator labour | 60 s at 300 per hour | 5.00 |
5. Consumables | Die spray per shot | 2.50 |
6. Die cost | 18,00,000 / 2,00,000 = 9.00, plus 2,00,000 / 2,00,000 = 1.00 | 10.00 |
Subtotal to casting | Steps 1 to 6 | 381.09 |
7. Rejection allowance | 4% of 381.09 | 15.24 |
8. Trimming | Press 5.00 plus labour 1.50 | 6.50 |
9. Shot blasting | Per piece | 2.00 |
10. Inspection and leak test | 4.00 plus labour 2.00 | 6.00 |
11. Overheads | 12% of conversion cost 91.25 (melting 19.25, casting 57.50, finishing 14.50) | 10.95 |
12. Packing | Per piece | 6.00 |
Total before profit | 427.78 | |
13. Profit | 10% of 427.78 | 42.78 |
Should-cost per piece | 470.56 |
Material is 68.8% of the cost before profit. Melting, casting and finishing together are 21.3%. The die is only 2.3%, which is why a tool cost that looks large on the purchase order moves the piece price so little at this volume.
How do you get casting cost per kg?
Divide the should-cost by the finished casting weight, not the shot weight. Rs 470.56 / 1.20 kg = Rs 392.13 per kg, about 1.7 times the ingot rate. Cost per kg is only a fair comparison between castings of similar weight, process and runner design.
What happens to casting cost when ingot price, melt loss or rejection change?
Change one input at a time and recalculate. This is the same calculation, with the base should-cost of Rs 470.56.
Change | New should-cost (Rs) | Change (Rs) | Change (%) |
|---|---|---|---|
Ingot rate up 8% (Rs 235 to Rs 253.80) | 497.50 | +26.94 | +5.7% |
Rejection at 8% instead of 4% | 487.33 | +16.77 | +3.6% |
Melt loss at 5% instead of 3% | 479.97 | +9.41 | +2.0% |
Runner weight 0.45 kg instead of 0.55 kg | 468.35 | -2.21 | -0.5% |
A lighter runner saves little because the runner metal is recycled. You save only the melting and the melt loss on it. Ingot rate and rejection are where the money is, so track them first.
How does casting cost change between sand, die and investment casting?
The formula stays the same. What changes is which lines dominate, so check these first for each process.
Process | Tooling | What drives cost | What is easy to miss |
|---|---|---|---|
Sand casting | Pattern and core boxes, low cost | Melting energy, moulding and core making, fettling and grinding | Yield (casting weight against metal poured) and sand and binder cost |
Gravity die casting | Metal die, medium cost | Cycle time, die coating, finishing | Die life and the labour on each cycle |
High pressure die casting | Metal die, high cost | Machine hour rate and cycle time, trimming, porosity rejection | Die maintenance and the rejection rate |
Investment casting | Wax pattern tooling, shell making | Wax, shell, dewax and burnout, cut-off and finishing, labour | Long process chain, so many small lines add up |
For auto parts, see how auto component costing works for how casting sits beside forging, machining and bought-out parts in a full BOM.
How do you check a foundry quote against casting cost?
Compare the quote to your should-cost, then ask which input explains the gap. Suppose the foundry quotes Rs 520 per piece. Against Rs 470.56 that is Rs 49.44, or 10.5%, higher. Per kg it is Rs 433.33 against Rs 392.13.
Test the likely causes one at a time. A rejection rate of 8% explains Rs 16.77. An ingot rate of Rs 260 per kg instead of Rs 235 explains Rs 35.82, about 72% of the gap. Ask the supplier for:
casting weight and shot weight
ingot rate and the date of the index it follows
melt loss and rejection percentages
cycle time and machine hour rate
die cost, die life and maintenance
overhead and profit percentages
For a wider method, read the manufacturing cost breakdown guide and how to estimate the cost of a new product.
What mistakes make a casting cost calculation wrong?
Charging the full shot weight at the ingot rate, when runners are re-melted.
Leaving melt loss out, or applying it to casting weight only.
Skipping the rejection allowance, or applying it to finishing that happens after rejects are removed.
Spreading die cost over the order quantity instead of the die life.
Using an old ingot rate with no date.
Adding labour to the machine hour rate and again as a separate line.
Comparing cost per kg across different parts.
Can you calculate casting cost in Excel, or do you need software?
Excel works for one casting. It struggles once you have hundreds of parts: an ingot rate change must reach every sheet, old versions get overwritten, and nobody can see who changed a machine hour rate. Costing software holds the rates once and recalculates every casting from them.
How does Cost It Right calculate casting cost?
Cost It Right (CIR) is costing software for every job in the cost chain, not one use case. For castings and the parts around them it gives you:
part and product costing for 24+ technologies, with standard costing formats for casting, ferrous casting, forging, machining, sheet metal, plastic and rubber
machine hour rate, labour, overheads and profit masters
raw material indexation with commodity price index (LME) and multiple external indexes
tool amortisation, tooling cost and tool amortisation reports
cost version history and version comparison
cost simulation and impact analysis up to finished-goods level, with bulk price amendments by Excel upload
supplier quote comparison against should-cost, vendor RFQ portal and reverse auction
BOM costing, ERP, PLM and CAD integration
costing sheet export, approval workflows and audit trail
That means a casting, its machining and its bought-out parts roll up in one cost sheet, and an ingot price move reaches every affected part.
See your own casting costed in Cost It Right. Book a demo.
FAQs
How do you calculate casting cost per piece?
Add material with melting loss, melting, casting machine time, labour, consumables and die amortisation. Then add a rejection allowance, finishing, overheads and packing, and finish with profit. In the worked example, an aluminium die-cast housing comes to Rs 470.56 per piece.
How do you calculate casting cost per kg?
Divide the total casting cost by the finished casting weight, not the shot weight. In the example, Rs 470.56 divided by 1.20 kg gives about Rs 392.13 per kg. Compare cost per kg only between castings of similar weight, process and runner design.
What is melt loss in casting cost?
Melt loss is metal lost as dross and oxidation during melting and holding, shown as a percentage of the metal melted. It is applied to the whole shot weight, including runners. At 3% on a 1.75 kg shot, the loss is 0.0525 kg.
Are runners and gating included in casting cost?
Runners, overflows and the biscuit are melted again, so they add melting cost and melt loss, but not the full metal price. Charging the full shot weight at the ingot rate overstates material. In the example it would add Rs 116.91 per piece.
How do you calculate die casting cost?
Use the same formula with a machine hour rate for the die casting machine, the cycle time, an operator, die spray and consumables. Add die cost and maintenance divided by shots over die life, a porosity rejection allowance, trimming, overheads, packing and profit.
How much does ingot price affect casting cost?
A lot, because material is the largest line. In the example it is 68.8% of the cost before profit, so ingot movements flow almost directly into price. An 8% rise in the ingot rate lifts the should-cost from Rs 470.56 to Rs 497.50, an increase of 5.7%.
What rejection rate should I use in casting cost?
Use your own rejection history for that part and process, not a default. The example uses 4% on cost up to casting. At 8%, the should-cost rises by Rs 16.77 per piece, so ask a foundry for its rate and how it measures it.
How is die or pattern cost added to casting cost?
Divide the tool cost plus maintenance by the number of shots over tool life, then add that per piece. In the example, Rs 18,00,000 over 2,00,000 shots is Rs 9.00 and maintenance is Rs 1.00, so the die adds Rs 10.00 per piece.
How do I check a foundry quote against casting cost?
Build your own should-cost, then compare line by line. Ask for casting and shot weight, ingot rate and index date, melt loss, rejection, cycle time, machine hour rate, die life, overheads and profit. Change one input at a time to see which explains the gap.
Is sand casting cost calculated differently from die casting?
The lines are the same, but different ones dominate. Sand casting is driven by melting energy, moulding, core making, fettling and yield. Die casting is driven by machine hour rate, cycle time, die cost and rejection. Pattern cost is usually lower than die cost.
Can I calculate casting cost in Excel?
You can for one casting, using the formula above. It becomes hard to manage across many parts, because rate changes must reach every sheet and versions get overwritten. Costing software keeps rates in one master and recalculates every casting when an input changes.
How does Cost It Right help with casting cost calculation?
Cost It Right has standard costing formats for casting and ferrous casting, with machine hour rate, labour, overheads and profit masters. It adds raw material indexation, tool amortisation, cost version history, simulation and impact analysis, supplier quote comparison and ERP, PLM and CAD integration.
Related Articles

Nov 12, 2026 • 11 min read
How to Calculate Sheet Metal Part Cost
Work out what a laser cut and bent sheet metal part should cost: material and scrap, machine time, setup, tooling, finishing, overheads and profit, in rupees.

Oct 26, 2026 • 9 min read
Machine Hour Rate (MHR): Formula, Calculation and Worked Examples for CNC and Press Machines
Learn the machine hour rate formula, which costs to include, and two worked examples in rupees for a CNC machining centre and a mechanical press.

Nov 16, 2026 • 12 min read
What Is Product Costing Software? Features, Types and Examples
See what product costing software does, how cost engineering tools differ from ERP costing, and a worked product cost in rupees, plus tools to shortlist.